What's new?

Drone flight over and through the construction site of the MKKD, September 2026
Movie: © Johannes Hauser

September 2026

The concrete floor is currently being poured and evenly distributed. Once the concrete has been laid, the surface will be smoothed promptly to ensure an even and as smooth as possible finish. This creates the foundation for the next stages of construction. We are very pleased with these visible signs of progress and will keep you updated on the next stages of construction.

August 2026

Work on the MKKD construction site is progressing: the underfloor heating has now been installed. Preparations for the concrete floor on the ground floor are currently underway. 

Juli 2026

Work is continuing apace at the MKKD building site: all the doors have now been fitted. Work is currently underway on the underfloor heating on the ground floor. We are delighted to see such visible progress and will keep you updated on the next stages of construction.

June 2026

Work is currently underway to waterproof the outer shell of the basement before the earthworks – and thus the landscaping of the outdoor area – can begin. At the same time, work is being carried out on the vestibule in the entrance area.